Green Power Sugar Limited, Gopuj
| Name Of Work |
Owner |
Remark |
| Construction of Diff.Machinery foundation/ Building extension & 10Mw.Co-generation project at Dhawarwadi. |
Jaywant Sugars Ltd., Karad, Dist – Satara. |
Work in progress |
| Construction of Civil structures for proposed Fipronil project at Lote,Parshuram, Tal-Chiplun, Dist-Ratnagiri. |
Ghrada Chemicals Limited, Dombivli(E), Dist- Thane |
Work in progress. |
| Construction of 18 MW Co-Generation Power Plant house, Boiler Foundation & Allied civil work, Chandrabhaganagar. |
Sahakar Shiromani Vasantrao Kale Sahakari Sakhar Karkhana Ltd, Chandrabhaganagar, Tal-Pandharpur, Dist-Solapur. |
Work in progress |
| Construction of 3500 TCD Sugar Factory, 16 MW Co-Gen. Project At – Gopuj Tal Khatav |
Green Power Sugars Ltd. At- Gopuj Tal – Khatav Dist – Satara |
Work in Progress |
Developer
| Construction of Main Factory Building, Machinery Foundation, Non Factory and Allied work at Dhawarawadi. |
Jaywant Sugars Ltd. Karad, Dist – Satara. |
Work Completed |
 |
| Construction of 2500 TCD Sugar Factory Main Factory Building & Machinery Foundation at Shirur. |
Venkteshkrupa Sugar Mill Ltd. Jategaon. Tal – Shirur, Dist – Pune. |
Work Completed |
 |
| Construction of Power House for co-Generation Plant at Yashwantnagar, Tal –Shirala |
Vishwasrao Naik S.S.K. Ltd. Chikali, Tal – Shirala. Dis-Sangali. |
Work Completed |
 |
| Construction of MCC Room for co-Generation Plant at Yashwantnagar, Tal –Shirala |
Vishwasrao Naik S.S.K. Ltd. Chikali, Tal – Shirala. Dis-Sangali. |
Work Completed |
 |
| Construction of Main Factory Building & Non Factory Building at Khardi |
Sitaram Maharaj S.K.Ltd. Khardi, Tal- Pandhrpur , Dist-Solapur |
Work Completed |
 |
| Construction of 4 MW Co-Generation Project at Chiplun. |
Three M Paper Manufacturing Co.Pvt Ltd. MIDC Kherdi, Tal – Chiplun Dist – Ratnagiri |
Work Completed |
 |
| Construction of New Finishing House at Chiplun. |
Three M Paper Manufacturing Co.Pvt Ltd. MIDC Kherdi, Tal – Chiplun Dist – Ratnagiri |
Work Completed |
 |
| Cooling Tower For Co-Generation at Rethare Tal Karad |
Y.M.Sahakari Sakhar K.LTD. Rethare Tal – Karad Dist Satara |
Work Completed |

|
| Cooling Tower For Co-Generation at Kundal, Tal – Palus, Dist-Sangli. |
Kranti Sahakari Sakhar Karkhan Ltd At Kundal, Tal-Palus, Dist - Sangli |
Work Completed |
 |
| Construction of Sugar Godown No. 11 for Sahyadri Sahakari Sakhar Karkhana Yashwantnagar, Karad |
Sahayadri Sahakari Sakhar Karkhana Ltd, Yashwantnagar, Tal -Karad, Dist- Satara |
Work Completed |
| Construction of Sugar
Godown & Store building for 2500 TCD Sugar Factory & 9.5Mw.
Cogeneration Project At.-Khandala,Tal-Khandala, Dist-Satara. |
Kisanveer Khandala Sahakari Sakhar Udyog, Khandala,Mhavashi. Tal- Khandala, Dist-Satara |
Work Completed |
| Construction of Biomass Power Project at MIDC Industrial Area Lonand Dist Satara |
Spark Green Energy (Satara) Ltd, Lonand Dist – Satara |
Work Completed |